Next Generation School
Champaign, IL
PK was selected to construct this new 2-story private school facility with gymnasium. After putting the foundations in during the fall, extreme winter weather shut the project down from Dec. 1 until late February. This 3 month delay would normally have added 3 months to the typical construction project. However, the owner asked PK to accelerate the schedule such that the building could be completed for an August opening of the new school year. PK came through in the nick of time, and school was open on time, with some very happy kids to enjoy this new leading private school facility in the area.